PROJECT
Construction and Commissioning Services for 200KMs. 24”dia. AHDEB Oil Field EXL1 (Phase I) Project
PRINCIPAL OWNER
Al Waha Petroleum Company Limited
CLIENT
China Petroleum Engineering & Construction Corporation (CPECC)
LOCATION
Al Wasit Governorate, IRAQ
REGION
Middle East
SERVICES
Construction and Commissioning
PROJECT SCOPE
Construction of 201KMs 24” dia. Oil Export Pipeline CPF00 to PS2 Project, Republic of IRAQ. (100bar pressure) including River & Major Canal crossings, 8 Block Valve Stations, Cathodic Protection System, Solar Power System and Lightning Protection System, Testing & Commissioning.
CONSTRUCTION CHALLENGES
- Most of the locations Water Table was very high, so the Contractor installed Set-on-Weights on the Pipeline
- Crossing of Al-Gharraf River by Float & Sink Method
RESULT
Achieved the required quality targets and met the timeline to support the completion of the entire scope by the Client / Main Contractor CPECC.