PROJECT
Crude Oil 100 Kms 48”Dia Pipeline Construction of Section IV – Abu Dhabi Crude Oil Pipeline Project (ADCOP)
PRINCIPAL OWNER
International Petroleum Investment Company (IPIC)
CLIENT
China Petroleum Engineering & Construction Corporation (CPECC)
LOCATION
Habshan – Fujairah, UAE
REGION
Middle East
SERVICES
Construction and Commissioning
PROJECT SCOPE
Construction of 100 Kms of 48”Dia. KP 272 to KP 382 with 5 Block Valve Stations, Road Crossings (Micro Tunnelling Method), Fiber Optic Communication System, SCADA System, Cathodic Protection System, Testing & Pre-Commissioning.
CONSTRUCTION CHALLENGES
- 60~70% works in Mountainous Section, Very Hard Rock, difficult to cut, do blasting works also
- Slopes between 20 to 45 degrees.
- Using the cable crane system for construction in mountainous section
- HDD Crossing at Sheikh’s Farm
- Crossing of Roads by Micro Tunneling Method
RESULT
Achieved the required quality targets and met the timeline to support the completion of the entire scope by the Client / Main Contractor CPECC.